Energy costs
Energy costs are significantly reduced.
Maintenance
The only known in-service use of fly-wheels in railways is a stationary fly-wheel storage system in a substation at Kölner Verkehrs-Betriebe AG (KVB), Cologne, Germany. There is however no data available on maintenance experience.
Maintenance experience with Magnetmotor fly-wheels used in Basel trolley busses
The maintenance intervals of the fly-wheels used in trolley busses in Basel are defined to 3500 operation hours. The manufacturer Magnetmotor claims that specific tests with bearings and lubrication prove that maintenance intervals of 6,000 h are possible and that for the power electronic the statistic MTBF (mean time between failure) is more than 40,000 hours.
Currently the maintenance of the MDS fly-wheel is done at Magnetmotor, i.e. the system has to be removed from the vehicle sent to the manufacturer. Typical maintenance includes checking of components and the system as a whole, cleaning and lubricating or exchanging the bearings. The average maintenance time is about one working day.
By 2000, the average repair requirements was down to one repair every 38,000 hours of operation (equivalent to one repair in 8 years per fly-wheel). |